High water table holds up pipework

Posted 21 Aug 2012 by stalbanscommunity Popular
Posted in Suburbs

The high water table is holding up wastewater pipe replacement work at the Bealey Avenue end of Champion Street and forcing a focus on Gresford Avenue end of Champion Street instead.

Work on the Bealey Avenue end will start again when the water level has lowered sufficiently. The work on champion Street is expected to be completed in about five weeks, according to SCIRT.

Source: SCIRT

This article was sourced from another website - view the original article.

Discussion

Related Items

Regenerate Christchurch signals approach to residential red zone

Regenerate Christchurch signals approach to residential red zone

Wednesday, 28 September 2016 4:24 p.m. by Regenerate Featured Popular
Introducing Matuku Takotako: Sumner Centre

Introducing Matuku Takotako: Sumner Centre

Monday, 26 September 2016 3:33 p.m. by GovtCCC Popular
Community invited to New Brighton Regeneration Hub

Community invited to New Brighton Regeneration Hub

Monday, 26 September 2016 3:10 p.m. by GovtCCC Featured Popular