Bower Avenue, Parklands, traffic island repair

Works Begin 16 Feb 2017 Works End
Works Status

Where: 452 to 499 Bower Avenue

When: Thursday 16 February 2017 for about one week

On Thursday 16 February 2017 we will begin a 3 stage traffic island repair programme on Bower Avenue. Please see the map below. Our normal work hours are between 7:00 am and 6:00 pm Monday to Friday with occasional weekend work as required.

Stage 1 - Will begin with a lane closure of the Western side of the traffic island at 497 Bower Avenue. We expect to be here for 3 days.

Stage 2 - We will swap the lane closure to the Eastern side of the traffic island 504 Bower Avenue. We expect to be here for 2 days.

Stage 3 - Set up a lane closure outside 452 Bower Avenue. We expect to be here for 2 days.

 

Traffic impacts 

  • Two-way traffic will be maintained during this work, by way of a stop-go system.
  • Parking on the street will not be available immediately next to the work area. No parking cones  will be in place to show this.
  • At times, footpath access will be disrupted. One side of the street will always be open for pedestrian use. Please follow our signs.

 

Start date: 
Thu, 16/02/2017
Project numbers: 
11032

Discussion