Parts of the northern part of Stanmore Rd in Richmond is closed due to major damage to shops in Richmond Village. Parts of the brick wall above Henry Africas has collapsed and the buildings are not able to be entered. Parts of the shops opposite have also been condemned. The front fascade of Richmond Garage on Petrie St around the corner has also fallen down and looks too dangerous to enter. Extensive cracks in the roads in Richmond north of North Avon Rd.

Brick building (Henry Africa’s) at north end of Stanmore Rd damaged, lost side wall.  Richmond garage frontage (Petrie Street) partly fallen off.  Lots of chimneys down or dodgy, many cracks in road, and water mains burst – ‘sand volcanoes’ in driveways etc.

Flesher Ave, River Rd zone c major land damage,our property has some of the worst liquification in CHCH our street still has sewerage issues, 8 houses in our street are unihabitable and 27 major claims over EQC cap, Henry Africas, Sweet Janes have gone, Methodist Church is badly damged, River Rd and surrounding roads badly damaged,basic work has been done on roads but still waiting for eqc reports to get a time line on remediation, coucils lack of oversight and inability to provide a comprehensive plan with resident/neighbourhood input is just adding to frustrations

 

Below are a list of works notices that are specific to Richmond, you can full a full list of Road and Work notices for Christchurch here.

Heywood Terrace - Lower Richmond - lift station installation, end of year shut down

Starts 18 Dec 2012, Ends
Added Friday, 4 January 2013 10:09 a.m. Active

Lower Richmond - wastewater renewal - end of year shutdown

Starts 18 Dec 2012, Ends
Added Friday, 4 January 2013 10:09 a.m. Active

Stapletons Road - Richmond - pressure wastewater tank installation *Update*

Starts 18 Dec 2012, Ends
Added Friday, 4 January 2013 10:09 a.m. Active

Randall Street - Richmond - wastewater replacement *Update*

Starts 18 Dec 2012, Ends
Added Friday, 4 January 2013 10:08 a.m. Active

Stapletons Road - Richmond - wastewater pipeline and lateral replacement *Update*

Starts 07 Jan 2013, Ends
Added Friday, 4 January 2013 10:08 a.m. Active

Guild Street and Slater Street - Richmond - wastewater renewal *Update*

Starts 13 Dec 2012, Ends
Added Friday, 4 January 2013 10:08 a.m. Active

Medway Street, Woodchester Avenue, Eveleyn Couzins Avenue - Richmond - watermain replacement

Starts 26 Nov 2012, Ends 21 Jan 2013
Added Friday, 23 November 2012 4:36 p.m.

Fitzgerald Avenue - Lower Richmond - wastewater renewal

Starts 26 Nov 2012, Ends 24 Dec 2012
Added Friday, 23 November 2012 10:56 a.m. Pending Completion

Chrystal Street, Lower Richmond - Wastewater renewal

Starts 12 Nov 2012, Ends 10 Dec 2012
Added Thursday, 8 November 2012 1:26 p.m. Pending Completion

Randall Street - Richmond - Wastewater pipeline and lateral

Starts 12 Nov 2012, Ends 16 Jan 2012
Added Tuesday, 6 November 2012 1:37 p.m. Pending Completion

Avalon Street and Hills Road, Lower Richmond - Lift station installation

Starts 29 Oct 2012, Ends 13 Nov 2012
Added Wednesday, 31 October 2012 3:07 p.m. Complete

McLeod Street - Lower Richmond - Wastewater renewal

Starts 23 Oct 2012, Ends 09 Nov 2012
Added Friday, 19 October 2012 11:56 a.m. Pending Completion

Champion Street, Lower Richmond, wastewater renewal

Starts 15 Oct 2012, Ends
Added Friday, 12 October 2012 4:36 p.m. Active

Petrie Street - Richmond - Wastewater pipeline and lateral repair

Starts 09 Oct 2012, Ends 30 Nov 2012
Added Wednesday, 10 October 2012 9:36 a.m. Pending Completion

Gresford Street - Lower Richmond - Wastewater renewal

Starts 08 Oct 2012, Ends 09 Nov 2012
Added Tuesday, 9 October 2012 3:36 p.m. Pending Completion

London Street - Lower Richmond - Wastewater renewal

Starts 01 Oct 2012, Ends 16 Nov 2012
Added Wednesday, 26 September 2012 5:06 p.m. Pending Completion

Perth Street - Lower Richmond - Road reconstruction

Starts 28 Sep 2012, Ends 12 Oct 2012
Added Wednesday, 26 September 2012 5:06 p.m. Pending Completion

Chrystal Street (in part) - Richmond - Wastewater pipeline and lateral replacement

Starts 01 Oct 2012, Ends
Added Wednesday, 26 September 2012 2:46 p.m. Complete

North Parade - Richmond - Wastewater pipeline and lateral repair

Starts 28 Sep 2012, Ends
Added Tuesday, 25 September 2012 5:46 p.m. Complete

Petrie Street - Lower Richmond - Road reconstruction

Starts 26 Sep 2012, Ends 12 Oct 2012
Added Tuesday, 25 September 2012 1:46 p.m. Pending Completion

Stapletons Road - Lower Richmond - Road reconstruction

Starts 26 Sep 2012, Ends 12 Oct 2012
Added Tuesday, 25 September 2012 1:26 p.m. Pending Completion

Dudley Street - Richmond - Road closure

Starts 19 Sep 2012, Ends 19 Oct 2012
Added Tuesday, 18 September 2012 5:26 p.m. Pending Completion

Dudley Street - Richmond - Wastewater pipeline and lateral replacement

Starts 17 Sep 2012, Ends 19 Oct 2012
Added Friday, 14 September 2012 5:16 p.m. Complete

Heywood Terrace - Richmond - Wastewater lift station installation

Starts 17 Sep 2012, Ends 23 Nov 2012
Added Friday, 14 September 2012 5:16 p.m. Pending Completion

Avalon Street - Richmond - Wastewater *Update*

Starts 12 Sep 2012, Ends
Added Wednesday, 12 September 2012 2:36 p.m. Active

Gresford Street and Trist Place - Lower Richmond - Road reconstruction

Starts 10 Sep 2012, Ends 22 Oct 2012
Added Thursday, 6 September 2012 3:16 p.m. Pending Completion

Alexandra Street - Lower Richmond - Road reconstruction

Starts 10 Sep 2012, Ends 19 Oct 2012
Added Thursday, 6 September 2012 2:36 p.m. Pending Completion

Champion Street - Lower Richmond - Wastewater

Starts 03 Sep 2012, Ends
Added Thursday, 6 September 2012 10:06 a.m. Active

Petrie Street - Richmond - Wastewater

Starts 03 Aug 2012, Ends 08 Nov 2012
Added Wednesday, 29 August 2012 1:26 p.m. Pending Completion

Nothing found

Nothing found

Nothing found

Below is information regarding the Fletcher/EQR Hub for Richmond.

Hub Name Mairehau Hub
Address 280 Westminster St, Mairehau
Phone Number 03 341 9995
Email Address clo.mairehau@eqr.co.nz
Notes Servicing: Papanui, St Albans, Mairehau, Shirley and Richmond.
Residential boundary areas include: Northcote Road – QE 2 Drive south.

Submit your own vision for Richmond

Suburb Discussion

News for this Suburb

Red Zone options miss the mark

Red Zone options miss the mark

Wednesday, 1 November 2017 11:31 a.m. by greeningtheredzone Featured Popular
Reconnecting the east to the city

Reconnecting the east to the city

Thursday, 12 October 2017 1:52 p.m. by AvonOtakaro Featured Popular
Children’s views shape the future of Christchurch

Children’s views shape the future of Christchurch

Wednesday, 28 June 2017 10:02 p.m. by Regenerate Popular
Southern Response to Step in on EQC Botched Repairs

Southern Response to Step in on EQC Botched Repairs

Monday, 26 June 2017 7:22 p.m. by Labour Featured Popular
MATARIKI RISES AGAIN IN THE RED ZONE

MATARIKI RISES AGAIN IN THE RED ZONE

Friday, 16 June 2017 12:02 p.m. by AvonOtakaro Featured Popular
Canterbury wellbeing data shows positive trends

Canterbury wellbeing data shows positive trends

Friday, 16 June 2017 11:52 a.m. by GovtBeehive Popular